Contract between Puerto Rico’s government and coal-fired plant operator leaves residents in the dark
View
Date:2025-04-15 18:56:09
SAN JUAN, Puerto Rico (AP) — A proposed amended contract between Puerto Rico’s government and the operator of a coal-fired power plant accused of contaminating low-income communities on the island drew scrutiny Monday during a heated public hearing.
Environmentalists and lawyers demanded to see the redacted details of the proposed amendments sought by AES Puerto Rico LP as they accused officials during the hearing held by Puerto Rico’s Energy Bureau of withholding key information that would affect those living in the U.S. territory.
“It can say anything under those blackouts,” said Víctor Alvarado, environmental affairs secretary for the Puerto Rican Independence Party.
“This is like a blank check,” added Myrna Conty Hernández, an environmentalist and community leader.
If approved, the amended contract would go into effect Dec. 1. It is expected to lead to an increase in power bills that are already among the highest of any U.S. jurisdiction and award more money to a company that has come under the scrutiny of the U.S. Environmental Protection Agency. The EPA is testing air and water in the region.
The Energy Bureau is expected to issue a decision in the coming days. A bureau spokeswoman said it does not comment on cases that are under review.
An AES spokesman did not immediately return a message seeking comment.
The amended contract already was approved by the governing board of Puerto Rico’s Electric Power Authority, which said the details are confidential because the contract still had to be approved by the Energy Bureau and a federal control board that oversees the island’s finances.
Puerto Rico’s power company has said that AES is facing “severe” financial issues and warned that if the company ceases to operate, the island’s already crumbling electric grid would be further destabilized and power bills would spike.
AES produces about one-quarter of Puerto Rico’s power via its coal-fired power plant in the southeast coastal town of Guayama.
Medical doctors have testified in public hearings that they’ve seen a “significant” increase in various types of cancers and other diseases in that region since the plant began operating.
“Approving this contract is mocking the victims,” said José Santos, with a local religious group. “Who is helping the citizens?”
The contract dating from 1994 has been amended twice. Among the new proposed amendments are details of a “green transition stabilization payment” and a plan to convert the Guayama coal plant to green energy, including the location of such projects. Such details have been redacted.
Attorney Ruth Santiago stressed that residents have a right to more information since public funds are involved.. She told Monday’s hearing that unrelated large-scale solar projects have led to an increase in flooding in some Puerto Rico communities and were built on agricultural land.
“These are issues that are going to affect them,” she said. “Instead of comments, we have questions.”
The contract calls for the closure of the coal generation plant by December 2027 as the island seeks to lessen its dependence on petroleum and transition to clean energy. Petroleum accounts for more than half of the island’s total energy use, according to the U.S. Energy Information Administration.
veryGood! (176)
Related
- Man can't find second winning lottery ticket, sues over $394 million jackpot, lawsuit says
- New Hampshire luxury resort linked to 2 cases of Legionnaires' disease, DPHS investigating
- West Virginia GOP delegate resigns to focus on state auditor race
- Trump’s vows to deport millions are undercut by his White House record and one family’s story
- Which apps offer encrypted messaging? How to switch and what to know after feds’ warning
- West Virginia GOP delegate resigns to focus on state auditor race
- Trump appeals Maine ruling barring him from ballot under the Constitution’s insurrection clause
- Thompson and Guest to run for reelection in Mississippi, both confirm as qualifying period opens
- Trump suggestion that Egypt, Jordan absorb Palestinians from Gaza draws rejections, confusion
- Justice Dept. accuses 2 political operatives of hiding foreign lobbying during Trump administration
Ranking
- Friday the 13th luck? 13 past Mega Millions jackpot wins in December. See top 10 lottery prizes
- To help rare whales, Maine and Massachusetts will spend $27 million on data and gear improvements
- What 2024's leap year status means
- These jobs saw the biggest pay hikes across the U.S. in 2023
- Newly elected West Virginia lawmaker arrested and accused of making terroristic threats
- A congressman and a senator’s son have jumped into the Senate race to succeed Mitt Romney in Utah
- Dalvin Cook, Jets part ways. Which NFL team could most use him for its playoff run?
- New Mexico regulators revoke the licenses of 2 marijuana grow operations and levies $2M in fines
Recommendation
IRS recovers $4.7 billion in back taxes and braces for cuts with Trump and GOP in power
North Carolina presidential primary candidates have been finalized; a Trump challenge is on appeal
What's open today? New Year's Day hours for restaurants, stores and fast-food places.
Trial of man charged with stabbing Salman Rushdie may be delayed until author’s memoir is published
Questlove charts 50 years of SNL musical hits (and misses)
Wife's complaints about McDonald's coworkers prompt pastor-husband to assault man: Police
Series of small explosions, no injuries reported after 1.7-magnitude quake in New York
Christina Hall Responds to Speculation She's Pregnant With Baby No. 4